Starting today, Tuesday, August 16 geotechnical drilling begins on 116 Avenue from 100 Street to the Bear Creek Bridges.

The geotechnical drilling is taking place to confirm asphalt and gravel thickness and to explore soil type and properties.

116 Avenue from 100 Street to the Bear Creek Bridges will remain open. Alternating one-lane traffic will be implemented as work progresses. Traffic will be reduced from two lanes to one lane when passing workers.

Throughout construction, the posted speed limit will be reduced to 30km/h. Drivers are advised to proceed with caution, watch for flag people and anticipate potential traffic delays.

The work is anticipated to be completed by August 20, weather permitting.

Information provided by the City of Grande Prairie