Aquatera has been working on installing a sanitary main along 84 Avenue, between 113 Street and 116 Street, as part of the Westpointe Sanitary Diversion Project. 

They are reporting now that unfortunately, due to unforeseen soil conditions, the work won’t be able to be completed until 2021. It was originally supposed to be compelted in August.  

Until the end of October, Aquatera will continue the installation of a manhole on the east side of 115 Street, south of 84 Avenue. The existing eastbound lanes will be closed, and traffic will remain routed to single lanes in both directions on the westbound lanes between 113 Street and 116 Street.  

Once the road repairs are complete, no further work will be conducted in 2020.